Milner’s Edge 11-Lot Residential Subdivision

Project Details

Location: Langley, BC
Client: Genaris Properties
Category: Environmental Construction, Residential, Subdivision & High-Density Multi-Family Development, Roadworks, Underground Utilities,
Scope: The development of an 11-lot subdivision in the Milner neighbourhood of Langely, BC, that included underground utility installation, roadworks, and environmental construction services.
J Cote icon

100mm Sanitary Force Main,

300mm Storm Main

Protecting the Local Ecosystem Without Disrupting Traffic

J.Cote worked with environmental consultants to install an 1800mm x 900mm concrete box wildlife tunnel under a heavy traffic roadway in Langley, BC. The concrete sections needed to be installed while maintaining single-lane traffic throughout the construction process.

Environmental Construction Completed On Schedule

To complete the wildlife tunnel, J.Cote installed a lock block retaining wall that included a 750mm concrete storm main that drains into an adjacent creek. All work including tunnel, retaining wall, backfill and landscaping were successfully completed within the 3-week environmental window.

J Cote icon

3 EA Headwalls,

3 Erosion & Sediment Control Stages

Roadworks,
Underground Utilities,

Campbell River, BC

Campbell River Waterfront Sewer Upgrades

Installation of 1300 LM of new 750mm PVC sewer main along Island Hwy 19A.